Task Plan
See Using Tasks and Task Plans for full details on the setup and configuration of task plans.
Task Plans can be Task Plans are used to run analysis from an action or models at a scheduled time (s)or from an action. There are also additional features which enable you to clear data and perform system tasks from within task plan.
Example
To setup a Task Plan which:
- Runs every day at 1am.
- Runs the Analysis Task 1, before Analysis Task 2.
Solution
- Create a new Task Plan in your application from within the repository.
- Tick
Enabled
andScheduled.
- Click
Insert excerpt _save _save nopanel true - Add your tasks,
- click the ellipses →
Add New Item
→Select your item
. - Complete the details and tick Mandatory if you want this task to complete before moving onto the next task back in your task plan.
- click the ellipses →
- Save your task, and repeat to add any additional tasks. Your Task plan will look similar to this:
- In the Schedule, complete the details, in our example we have set the Task Plan to run everyday at 1am. Note: * means all values, and ? means no value. You will find more information on this in the the Task Plan Plans help pages mentioned above.
More Information